Question: Using schedule performance index (SPI) and cost performance index (CPI), is the project ahead or behind budget and schedule? EARNED VALUE ANALYSIS DATA End of

Using schedule performance index (SPI) and cost performance index (CPI), is the project ahead or behind budget and schedule?

EARNED VALUE ANALYSIS DATA
End of Week 30
Task Description Estimated Activity Cost Actual Expenses Status Report % Complete
A Requirements $ 10,000 $ 12,424 100%
B Market Assesment $ 20,000 $ 20,157 100%
C Design $ 15,000 $ 26,369 100%
D Development $ 45,000 $ 63,797 100%
E Testing $ 10,000 $ 11,012 100%
F Revisions $ 15,000 $ 9,025 40%
G Documentation $ 20,000 $ 19,819 100%
H Quality Assurance $ 10,000 $ 14,483 80%
I Pricing $ 5,000 $ 6,521 100%
J Production $ 40,000 $ - 0%
K Distribution $ 15,000 $ - 0%

Using schedule performance index (SPI) and cost

Weeks 1 23 Weeks Weeks 10 | 11 | 12 | 13 | 14 | 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Weeks 33 34 35 36 37 4 5 6 7 8 9 Tasks A B D E F G H J K

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!