Question: Using Table 7 . 2 , if the expected times for activities A , C , and H increased by 3 , 3 , and

Using Table 7.2, if the expected times for activities A, C, and H increased by 3,3, and 4 weeks, respectively, by how many weeks
would the project's earliest expected time of completion increase?
A. greater than 2 weeks but fewer than or equal to 4 weeks
B. greater than 6 weeks
C. no change
D. greater than 4 weeks but fewer than or equal to 6 weeks