Question: Using Table 7 . 2 , if the expected times for activities A , C , and H increased by 3 , 3 , and
Using Table if the expected times for activities A C and H increased by and weeks, respectively, by how many weeks
would the project's earliest expected time of completion increase?
A greater than weeks but fewer than or equal to weeks
B greater than weeks
C no change
D greater than weeks but fewer than or equal to weeks