Question: Using table Q4c below, draw an network diagram, calculate float for each task using earliest and latest event times and determine the following: i)Total

Using table Q4c below, draw an network diagram, calculate float for each

Using table Q4c below, draw an network diagram, calculate float for each task using earliest and latest event times and determine the following: i)Total project duration ii) Critical path Table Q4c Activity/Task A BCDEF C D G H Preceding Activities A B B B C,D D E,G Time Estimate (weeks) m a 8 11 7 6 10 6 5 4 10 12 12 6 14 10 10 8 b 16 14 19 6 20 10 17 11 (note: average task durations may be numerically rounded to the nearest whole number)

Step by Step Solution

3.46 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Based on the given data we first find the expected duration and variance for each activity as shown ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!