Question: Using the 7 w ' s questions for the purpose of implementing project risk management in an organization, the question Who? relates to Question

Using the "7 w's questions" for the purpose of implementing project risk management in an organization, the question "Who?" relates to
Question 4 options:
a)
Define a sponsor at the corporate level
b)
Assign a project manager
c)
Define an implementation team
d)
Parties involved in the implementation