Question: Using the assembly - line balancing procedure, which of the following is the required cycle time in minutes if the task times for the seven

Using the assembly-line balancing procedure, which of the following is the required cycle time in
minutes if the task times for the seven tasks that make up the assembly line are 7,5,6,6,5,7, and 6
minutes, and the assembly line is required to produce 200 products?
a.7
b.6
c. Cannot be determined from the information above
d.4.76
e.8