Question: Using the assembly - line balancing procedure, you have just determined the actual number of workstations that will be used on an assembly line to

Using the assembly-line balancing procedure, you have just determined the actual number of
workstations that will be used on an assembly line to be 6. The cycle time of the assembly line is 5
minutes and the sum of all tasks required on the line is 24 minutes. Which of the following is the
correct value for the assembly line's efficiency?