Question: Using the attached network diagram, complete a resource load chart for a construction project, assume that there are only three cranes available and given this
Using the attached network diagram, complete a resource load chart for a construction project, assume that there are only three cranes available and given this resource constraint, apply the following heuristics:
minimum slack
smallest duration
lowest identification number
A In what order will you load activities?
B What is the revised slack in days for Activity F after completing the resource load chart?
C Why is Activity F scheduled before Activity E even though they are both scheduled to start in time period
D What is Activity Bs start time and revised slack?