Question: Using the Beta distribution, calculate the Expected Activity Distribution ( EAD ) , Standard Deviation and Range of Estimate Which activity has the most risk?

Using the Beta distribution, calculate the Expected Activity Distribution (EAD), Standard Deviation and Range of Estimate Which activity has the most risk? Which activity has the less risk? Answers must be in 3 decimal place.
Activity
P
M
O
J
37
20
16
K
79
60
41
L
49
44
38
M
31
27
23
Expected Activity Duration (Beta Distribribution)
Beta Activity Standard Deviation
Range of Estimate-Start
Range of Estimate-End
22.167
3.5
60.00
53.667
43.833
Activity J (P =37, M =20, O =16):
37+4(20)+16/6=37+80+16/6=133/6=22.167
Activity K (P =79, M =60, O =41):
79+4(60)+41/6=79+240+41/6=360/6=60.00
Activity L (P =49, M =44, O =38):
49+4(44)+38/6=49+
Activity M (P =31, M =27, O =23):
What is the expected activity Duration for Activity L?
A.43.667
B.44.667
C.45.167
D.43.833
What is the start range for Activity K?
A.53.667
B.60.000
C.54.333
D.53.467
What is the standard deviation for Activity J?
A.3.0
B.3.5
C.3.467
D.2.667
Which activity has the lesser risk?
A. J
B. K
C. L
D. not sure
What is the standard deviation for Activity L?
A.1.83
B.1.333
C.2.833
D.1.833
Which activity has the most risk?
A. J
B. K
C. L
D. not sure

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!