Question: Using the BOM shown below, 1 week B (2) 1 week (1) 2 weeks D(4) 4 weeks E(1) 32 weeks F(1) 6.2 weeks C (2)

Using the BOM shown below, 1 week B (2) 1 week
Using the BOM shown below, 1 week B (2) 1 week (1) 2 weeks D(4) 4 weeks E(1) 32 weeks F(1) 6.2 weeks C (2) 2 weeks E (3) 3.2 weeks a. How many of part E will be needed if 20 units of end Item A are needed? Number of parts needed E b. How many part Cs will be needed? Number of parts needed