Question: Using the BOM shown below. 2 weeks B (5) 1 week C(2) 3 weeks D (3) 3 weeks E (2) 3.5 weeks F(2) 5.5 weeks

Using the BOM shown below. 2 weeks B (5) 1 week

Using the BOM shown below. 2 weeks B (5) 1 week C(2) 3 weeks D (3) 3 weeks E (2) 3.5 weeks F(2) 5.5 weeks C (3) 3 weeks E (2) 3.5 weeks What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.) Cumulative lead time weeks