Question: Using the BOM shown below, A 3 weeks B (2) 1 week C(2) 1 week D(3) 2 weeks C(1) E(3) E (4) 2.2 weeks F(3)

Using the BOM shown below, A 3 weeks B (2) 1 week

Using the BOM shown below, A 3 weeks B (2) 1 week C(2) 1 week D(3) 2 weeks C(1) E(3) E (4) 2.2 weeks F(3) 3.2 weeks 1 week 2.2 weeks What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.) Cumulative lead time weeks