Question: Using the bottleneck product mix decision method, which product should be selected first? Product W X Y Z Contribution margin per unit $4.50 $5.95 $2.20
Using the bottleneck product mix decision method, which product should be selected first? Product W X Y Z Contribution margin per unit $4.50 $5.95 $2.20 $3.85 Minutes of processing time at the bottleneck per unit 10 5 2 6 A. Z B. Y C. X D. W