Question: Using the CPM analysis below, which activities make up the critical path? A-C-D-E A-C-B-D-E A-B-D-E A-D-E 2.Using the CPM analysis below, what is the completion
Using the CPM analysis below, which activities make up the critical path?
| A-C-D-E | ||
| A-C-B-D-E | ||
| A-B-D-E | ||
| A-D-E |
2.Using the CPM analysis below, what is the completion time for the project?
A. 9 days
B. 8 days
C. 7 days
D. None of the above
3.Using the CPM analysis below, if there is slack, which activity has slack and how many days?
| A. D - 3 days | ||
| B. B - 3 days | ||
| C. C - 2 days | ||
| D. C - 1 day |