Question: Using the CPM analysis below, which activities make up the critical path? A-C-D-E A-C-B-D-E A-B-D-E A-D-E 2.Using the CPM analysis below, what is the completion

Using the CPM analysis below, which activities make up the critical path?

A-C-D-E

A-C-B-D-E

A-B-D-E

A-D-E

2.Using the CPM analysis below, what is the completion time for the project?

A. 9 days

B. 8 days

C. 7 days

D. None of the above

3.Using the CPM analysis below, if there is slack, which activity has slack and how many days?

A. D - 3 days

B. B - 3 days

C. C - 2 days

D. C - 1 day