Question: Using the CPM approach and using the most likely estimate what is the critical path: a . A - B - C b . A
Using the CPM approach and using the most likely estimate what is the critical path:
a ABC
b ABCDF
c ABCF
d ABDF
Using the PERT approach what is the critical path:
a ABC
b ABCDF
c
d ABDF
Using the most likely estimates and applying the critical chain approach, what will be the project
duration?
a days
b days
c days
d days
Using the most likely estimates, how many slack days is there in the project?
a days
b days
c days
d days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
