Question: Using the data below for four jobs at a work center, calculate the critical ratio for each job and determine the order in which the

Using the data below for four jobs at a work center, calculate the critical ratio for each job and determine the order in which the jobs should be sequenced based on the Critical Ratio. Assume today is day 220

Job

Due Date

Lead time Remaining (days)

Actual Time Remaining

Critical Ratio

Sequence

P

240

5

Q

235

18

R

232

9

S

225

8