Question: Using the data below for four jobs at a work center, calculate the critical ratio for each job and determine the order in which the
Using the data below for four jobs at a work center, calculate the critical ratio for each job and determine the order in which the jobs should be sequenced based on the Critical Ratio. Assume today is day 220
| Job | Due Date | Lead time Remaining (days) | Actual Time Remaining | Critical Ratio | Sequence |
|
| P | 240 | 5 |
|
|
|
|
| Q | 235 | 18 |
|
|
|
|
| R | 232 | 9 |
|
|
|
|
| S | 225 | 8 |
|
|
|
|
|
|
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts