Question: Using the data, create the project schedule using normal times. In all-crash mode. Identify how much it would cost to crash the schedule by 2,4,6,8
Using the data, create the project schedule using normal times. In all-crash mode. Identify how much it would cost to crash the schedule by 2,4,6,8 days

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash Cost per Day A 12 200 9 350 B 8 300 8 300 c 250 7 450 D B 6 400 5 600 E B, C 5 150 4 225 F 10 500 9 650 G D,E,F 400 900