Question: Using the data from Figures 1214, develop net material requirements plan for 50 units of item A assuming that it takes only 1 unit of

Using the data from Figures 1214, develop net material requirements plan for 50 units of item A assuming that it takes only 1 unit of item B for each unit of item A.

Using the data from Figures 1214, develop netUsing the data from Figures 1214, develop netUsing the data from Figures 1214, develop net

FIGURE 12 Material Structure Tree for Item A Material Structure Tree for Item A Level 0 1 B(2) C(3) 2 2 D(2) E(3) E(1) F(2) Week FIGURE 13 Gross Material Requirements Plan for 50 Units of A 1 2 3 4 5 6 Required Date 50 A Lead Time = 1 Week Order Release 50 Every part A requires 2 part B's in week 5 T100 Required Date B Lead Time = 2 Weeks Order Release 100 Required Date 150 Lead Time = 1 Week Order Release 150 Required Date 200 D Lead Time = 1 Week Order Release Required Date 300 150 E Lead Time = 2 Weeks Order Release 300 150 Required Date 300 F Lead Time = 3 Weeks Order Release 300 Week FIGURE 14 Net Material Requirements Plan for 50 Units of A Item Lead Time 1 N 3 3 4 5 5 6 1 Week Gross On-Hand 10 Net Order Receipt Order Release 50 10 40 -40 40* B 2 Weeks Gross On-Hand 15 Net Order Receipt Order Release 80 15 65 65 65 1 Week Gross On-Hand 20 Net Order Receipt Order Release 120 20 100 - 100 100 D 1 Week Gross On-Hand 10 Net Order Receipt Order Release 130 10 120 120 120 E 2 Weeks Gross On-Hand 10 Net Order Receipt Order Release 195 10 185 185 100 0 100 100 185 100 F 2009 3 Weeks Gross On-Hand 5 Net Order Receipt Order Release 5 195 195 195

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!