Question: Using the data from Problem 1. ActivityDuration (weeks) Activity... | Chegg.com 2a. Suppose the following data is given about the cost associated with crashing activities.
Using the data from Problem 1. ActivityDuration (weeks) Activity... | Chegg.com
2a. Suppose the following data is given about the cost associated with crashing activities. What activities should be crashed, and how much will it cost if the deadline is changed to:
- 19 weeks
- 18.5 weeks
- 18 weeks
- 17.5 weeks
- 17 weeks
- 16.5 weeks
- 16 weeks
- 15.5 weeks
- 15 weeks
| Time | Cost ($1,000s) | |||
| Activity | Normal | Crash | Crash | Normal |
| A | 2.5 | 1.5 | 135 | 90 |
| B | 3.5 | 3.0 | 70 | 50 |
| C | 2 | 1.4 | 180 | 135 |
| D | 3 | 2.3 | 155 | 135 |
| E | 1.5 | 1.0 | 150 | 110 |
| F | 2 | 1.4 | 70 | 55 |
| G | 4 | 3 | 90 | 75 |
| H | 1.5 | 1.0 | 80 | 50 |
| I | 2 | 1.4 | 70 | 45 |
| J | 4.5 | 3.4 | 170 | 125 |
| K | 2.5 | 1.7 | 95 | 65 |
| L | 1 | 0.7 | 140 | 110 |
| M | 2.5 | 1.9 | 135 | 100 |
| N | 3.5 | 2.5 | 65 | 35 |
| O | 1.5 | 1.2 | 145 | 130 |
| P | 2.5 | 2.0 | 85 | 55 |
| Q | 4.5 | 3.0 | 110 | 95 |
2b. Plot the cost of time reduction against total time reduction and draw any conclusions. What happens to the cost as the amount of time reduction is increased?
Step by Step Solution
There are 3 Steps involved in it