Question: Using the data given in the following table, what is the latest finish time for activity D Activity Predecessor A B C A B All

Using the data given in the following table, what is the latest finish time for activity D Activity Predecessor A B C A B All times in days m b 11 2 3 2 6 5 6 7 9 9 10 8 12 16 7 19 G H D D E.FI O a. between 6 and 8 days O b. between 8 and 10 days O c. more than 10 days O d. between 4 and 6 days