Question: Using the data table below, calculate the expected completion time of the project. Predecessor Duration A - 5 B A 3 C A 2 D

Using the data table below, calculate the expected completion time of the project.

Predecessor Duration

A - 5

B A 3

C A 2

D C 4

E B,D 4