Question: Using the data table below, calculate the expected completion time of the project. Predecessor Duration A - 5 B A 3 C A 2 D
Using the data table below, calculate the expected completion time of the project.
Predecessor Duration
A - 5
B A 3
C A 2
D C 4
E B,D 4