Question: Using the Decision tree analysis formula, compute for the EV. HIJ Contractors has to decide whether to prepare a bid or not. The proposal Bid

Using the Decision tree analysis formula, compute for the EV.

HIJ Contractors has to decide whether to prepare a bid or not. The proposal Bid Cost 4,000.00. If the Bid is submitted the probable contract award is 60%. If the company is awarded the contract, it may earn an income of 70,000.00 or pay a fine of 10,000.00 if it fails. The probability of success estimated to be 70%.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To compute the Expected Value EV using decision tree analysis we nee... View full answer