Question: Using the distribution requirements planning information provided below, what periods of the master production schedule would have net requirements? On - hand = 2 5

Using the distribution requirements planning information provided below, what periods of the master production schedule
would have net requirements?
On-hand =25 units, safety stock =15 units, shipping quantity =50 units, transit time =1 week
Answers
Periods 1,3, and 5
Periods 2,4, and 5
Periods 3 and 5