Question: Using the dual - rate method, compute the amount allocated to the Machining and Assembly Departments when ( a ) the budgeted fixed - cost
Using the dualrate method, compute the amount allocated to the Machining and Assembly Departments whena the budgeted fixedcost rate is calculated using budgeted fixed costs and practical capacity of the Materials Management Department, b fixed costs are allocated based on the budgeted fixedcost rate and budgeted usage of Materials Management Department services by the Machining and Assembly Departments, andc variable costs are allocated using the budgeted variablecost rate and actual usage.