Question: Using the early start schedule for the project given below, determine the maximum overdraft and total interest costs. Plot the total costs, total payments after

Using the early start schedule for the project
Using the early start schedule for the project given below, determine the maximum overdraft and total interest costs. Plot the total costs, total payments after delay, and overdraft. Solve the problem using the Excel spreadsheet (use appropriate formulas in the spreadsheet cells when it is necessary). Assume the retainage is ten percent (10%) by both client and contractor; markup is five percent (5%); the interest rate is one percent (1%) per month; and there are four (4) weeks in a month. The total indirect cost is $5,032. Activities B, F, and K are subcontracted. The payment is received one month after billing (i.e., two month delay). Number Activity Duration Total Activity Followers (weeks) Cost $ 1600 1000 1 2 3 4 5 6 7 8 9 10 11 COOWLOI-X 2 2 1 4 5 8 6400 2500 8000 2000 4 5,6 7 8 9 10 10 11 J 4 5 3 800 3500 4200

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!