Question: Using the EDD ( earliest due date ) decision rule for sequencing the jobs, the order is ( to resolve a tie, use the order

Using the EDD(earliest due date) decision rule for sequencing the jobs, the order is(to resolve a tie, use the order in which the jobs were received):
Part 11Part 12Part 13Part 14
Sequence
Job
1
DE-06
RG-05
CX-01
SY-11
BR-02
2
DE-06
SY-11
BR-02
CX-01
RG-05
3
CX-01
DE-06
RG-05
SY-11
BR-02
4
RG-05
SY-11
BR-02
CX-01
DE-06
5
BR-02
RG-05
DE-06
CX-01
SY-11
Part 15
The total flow time for the sequence developed using the EDD rule=
enter your response here days (round your response to two decimal places).
Part 16
The percentage utilization for the sequence developed using the EDD rule=
enter your response here%(enter your response as a percentage rounded to two decimal places).
Part 17
The average number of jobs in the system for the sequence developed using the EDD rule=
enter your response here jobs (round your response to two decimal places).
Part 18
The average tardiness(job lateness) for the sequence developed using the EDD rule=
enter your response here days (round your response to two decimal places).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!