Question: Using the EOQ model under certainty, calculate the recommended inventory level for Metals LCC. Question: solve for Q and show the calculations. V=$50.00perunitW=15%S=$7.50perunitperyearA=$50.00perorderR=1,200units Now that


Using the EOQ model under certainty, calculate the recommended inventory level for Metals LCC. Question: solve for Q and show the calculations. V=$50.00perunitW=15%S=$7.50perunitperyearA=$50.00perorderR=1,200units Now that you have the recommended quantity for the initial inventory level, calculate the point of reordering for Metals LCC. Assume that order transmittal takes two days, order processing and preparation take two days, and order delivery takes five days. This results in a replenishment or lead time of nine days. Given that demand is 15 units per day. Question: What is the reordering point for Metals LCC? show the calculations
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts