Question: Using the EPQ model, what is the cycle time in days if the usage rate is 1,000 units per day and the EPQ amount is
Using the EPQ model, what is the cycle time in days if the usage rate is 1,000 units per day and the EPQ amount is 8,000 units and the production rate is 1,500 units per day? Select the closest answer.
| 0.125 days | ||
| 0.1875 days | ||
| 5 days | ||
| 8 days |