Question: Using the FCFS (first come first served) decision rule for sequencing the jobs the order is Sequence Job The following jobs are waiting to be

Using the FCFS (first come first served) decision
Using the FCFS (first come first served) decision
Using the FCFS (first come first served) decision
Using the FCFS (first come first served) decision
Using the FCFS (first come first served) decision
Using the FCFS (first come first served) decision rule for sequencing the jobs the order is Sequence Job The following jobs are waiting to be processed at Rick Solano's machine center Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day) Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241 Job Due Date BR-02 CX-01 DE-06 RG-05 SY-11 Date Job Received 230 235 231 228 225 320 360 310 300 270 Duration (days) 35 40 30 15 25 The total flow time for the sequence developed using the FCFS rule = days (round your response to two decimalplaces). The percentage utilization for the sequence developed using the FCFS rule = %(enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the FCFS rule = jobs (round your response to two decimalplaces). The average tardiness (job lateness) for the sequence developed using the FCFS rule = days (round your response to two decimalplaces). Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence Job 1 2 3 4 The total flow time for the sequence developed using the EDD rule = days (round your response to two decimalplaces). The percentage utilization for the sequence developed using the EDD rule = _%( enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the EDD rule = _jobs (round your response to two decimalplaces). The average tardiness (job lateness) for the sequence developed using the EDD rule = Lu_days (round your response to two decimalplaces). Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve atie, use the order in which the jobs were received): Sequence Job 1 2 3 3 4 5 The total flow time for the sequence developed using the SPT rule = days (round your response to two decimalplaces). The percentage utilization for the sequence developed using the SPT rule = 96 (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the SPT rule = jobs (round your response to two decimalplaces), The average tardiness (job lateness) for the sequence developed using the SPT rule = days (round your response to two decimalplaces). Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence Job 1 2 3 4 5 -- The total flow time for the sequence developed using the LPT rule = days (round your response to two decimalplaces). The percentage utilization for the sequence developed using the LPT rule = _%(enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the LPT rule = __jobs (round your response to two decimalplaces). The average tardiness (job lateness) for the sequence developed using the LPT rule = _days (round your response to two decimalplaces)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!