Question: Using the FCFS rule for scheduling, the sequence is 3-2-1 2-3-1 1-3-2 3-1-2 2-1-3 1-2-3 . Sunny Park Tailors has been asked to make three
Using the FCFS rule for scheduling, the sequence is
3-2-1
2-3-1
1-3-2
3-1-2
2-1-3
1-2-3
.
Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits.
| Times Taken for Different Activities (hours) | ||
| Suit | Cut and Sew | Deliver |
| 1 | 4 | 2 |
| 2 | 7 | 7 |
| 3 | 6 | 5 |
Assume that orders for suits have been listed in the above table in the order in which they were received.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts