Question: Using the figure below, answer the following: 1. Calculate the ES, EF, LS, and LF times and the slack time for each activity. 2. Identify

Using the figure below, answer the following: 1. Calculate the ES, EF, LS, and LF times and the slack time for each activity. 2. Identify the critical path for the project. 3. Can the project be completed in 30 weeks? 4. Assume that "Systems Analysis actually finished at 8 weeks, Design Input & Output" actually finished at 16 weeks, and Design Database actually finished at 19 weeks. Recalculate the expected project completion time. 5. Which activities would you focus on to get the project back on schedule? Develop Input Screens 5 Design Input & Output 3 3 Problem Definition System Analysis Test System Implement System Develop Output Reports 6 10 1 2 2 5 8 6 9 5 Design Database Develop Database 4 15 2