Question: Using the First Come First Serve Scheduling algorithm, show the Gantt chart for the scheduled processes and compute the average waiting time. Suppose the processes

Using the First Come First Serve Scheduling algorithm, show the Gantt chart for the scheduled processes and compute the average waiting time. Suppose the processes arrive in the order P2, P3, P4, P1, P5. Burst Time Process P1 P2 P3 P4 P5 15 10