Question: Using the following Burndown table for a 6-day Sprint, answer the following questions: Day Done Remaining Ideal Done Per Day Ideal Velocity Initial value 0
Using the following Burndown table for a 6-day Sprint, answer the following questions: Day Done Remaining Ideal Done Per Day Ideal Velocity Initial value 0 0 1 3 2 5 3 4 4 7 5 10 6 13 What's the Total work to be Done