Question: Using the following cost allocations, determine the total overhead allocation for Batch B. Activity Cost Allocation Purchasing $20 per Purchase Order Receiving $5 per Shipment
Using the following cost allocations, determine the total overhead allocation for Batch B. Activity Cost Allocation Purchasing $20 per Purchase Order Receiving $5 per Shipment Machine Set-Ups $50 per Setup Quality Control $10 per Inspection Batch B used the following; 10 Purchase Orders; 20 Shipments received; 20 Setups; 30 Inspections; and 35 Direct Labor Hours. What is the TOTAL overhead allocation using ABC.