Question: Using the following data, Answer the following questions for PERT. Immediate Activity Predecessor Time A - 1 B - 4 C A 2 D B

Using the following data, Answer the following questions for PERT. Immediate
Activity Predecessor Time
A -1
B -4
C A 2
D B 2
E C 3
F D 2
a. What is the Critical Path?
b. What is the length of the critical path?
c. Which is not a path
1. CGK
2. BGK
3. CGHK
4. DHK