Question: Using the following data develop a precedence network diagram. Then calculate the corresponding CPM values and clearly mark the critical path. Note that activities C

Using the following data develop a precedence network diagram. Then calculate the corresponding CPM values and clearly mark the critical path.
Note that activities C and D are contiguous, whereas the rest are all interruptible.
\table[[Activity,IPA,Relationship,Duration],[A,-,,],[B,A,SS-2,],[,,FF-1,],[C,B,SS-1,],[,,FF-4,],[D,C,SS-3,],[,,FF-2,],[E,D,SS-2,],[,,FF-1,],[F,E,SS-1,],[,,FF-2,]] Durations are A-5 B-8 C-11 D3 E8 F2
Using the following data develop a precedence