Question: Using the following information a) Determine the absolute minimum time it will take to complete the project if the project is crashed as far as
Using the following information

a) Determine the absolute minimum time it will take to complete the project if the project is crashed as far as possible.
Shortest critical path = weeks
b) Calculate the additional cost associated with this approach to the project if it is crashed as far as possible.
Additional Cost = $
Normal Immediate Time Activity Predecessor(s) (weeks) none 10 none A,B Crash Time (weeks) 8 3 Normal Cost $16,000 6,000 12,000 7,000 28,000 4,500 7,200 5,000 15,000 7,000 10,000 24,000 Crash Cost $20,000 9,000 24,000 10,000 34,000 4,500 9,000 5,000 18,000 7,000 11,000 24,000 C, D, E HI K 1 0 10Step by Step Solution