Question: Using the following information about Project B, its activities and predecessor activities below: Predecessors Activity A D, E H F, G 2. Create the Activity

Using the following information about Project B, its activities and predecessor activities below: Predecessors Activity A D, E H F, G 2. Create the Activity Network Diagram using the (AoN) technique. b. Label all the nodes appropriately (as above) C. Identify the merge activities (Merge activities are G and H) d Identify the burst activities (Burst activities are A and C)