Question: Using the following information and network, develop the optimal project crashing. This project has $1,000 per day for crashing (Indirect project costs) 6 10 2
Using the following information and network, develop the optimal project crashing. This project has $1,000 per day for crashing (Indirect project costs)


6 10 2 f 5 5 d Using the following information and network, develop the optimal project crashing. This project has $1,000 per day for crashing (Indirect project costs) Normal Crash Cost per Activity Duration (days) Duration (days) Day to Crash a 6 6 b 10 8 $500 5 4 300 d 4 1 700 9 7 600 f 2 1 800