Question: Using the following information: Corrective Corrective WBS BCE Element BTE (wks) Cost Time Likelihood Predecessor A 20000 6 4000 2 .2 B 16000 7 4000

Using the following information: Corrective

Using the following information: Corrective Corrective WBS BCE Element BTE (wks) Cost Time Likelihood Predecessor A 20000 6 4000 2 .2 B 16000 7 4000 2 .3 A 32000 5 8000 3 .3 B D 20000 4 12000 3 .2 A E 16000 6 6000 2 .3 B,D a. Determine the risk time and risk cost for each WBS elements. b. What is the project expected cost (BC) and expected time (ET)? C. Which activities should be watched because the pose the highest risk