Question: Using the following information, what is the joint probability for the three paths to be completed in 25 days or less while recognizing that in

Using the following information, what is the joint probability for the three paths to be completed in 25 days or less while recognizing that in practice it is possible for noncritical paths to take longer than expected? Using the following information, what is the

a.

0.0419

b.

0.5000

c.

0.3311

d.

some other value

e.

0.0000

Path Path Path Duration Standard Deviation 1-2-5-7 24 days 2.236 days 1-3-7 22 days 1.414 days 1-4-6-7 25 days 2.000 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!