Question: Using the following project Information, calculate the variance for each of the project activities. Optimistic Time Most Likely Time Pessimistic Time Immediate Activity Estimate(weeks) Estimates

Using the following project Information,
Using the following project Information,
Using the following project Information, calculate the variance for each of the project activities. Optimistic Time Most Likely Time Pessimistic Time Immediate Activity Estimate(weeks) Estimates (weeks) Estimates (weeks) Predecessor(s) P 3 6 9 none B 3 5 7 4. 7 12 A D 4 8 10 B E 5 10 16 F 3 4 5 DE 3 6 8 DE H 5 6 10 F I 5 8 11 3 3 3 3 H, Activity Variance . B C D E F G H I 3