Question: Using the following project information table [ [ Activity , table [ [ Optimistic Time ] , [ Estimate ( weeks ) ]

Using the following project information
\table[[Activity,\table[[Optimistic Time],[Estimate(weeks)]],\table[[Most Likely Time],[Estimates (weeks)]],\table[[Pessimistic Time],[Estimates (weeks)]],\table[[Immediate],[Predecessor(s)]]],[A,2,3,5,none],[B,2.6,4,5,A],[C,5,7,8,A],[D,3,5,8,B, C],[E,4,6,13,B, C],[F,2,5,8,D],[G,4,5,7,E],[H,6,6,9,F],[I,4,8,11,H, I]]
The critical path is A-C-E-G-I-J.
\table[[Activity,A,B,C,D,E,F,G,H,I,J],[Variance,0.25,0.16,0.25,0.69,2.25,1.00,0.25,0.25,1.36,0.03]]
(a) Calculate the probability that the project will be completed in 31 weeks. (Round your answer to 4 decimal places, e.g.1.7945.)
project 31
(b) Calculate the probability that the project will be completed in 35 weeks. (Round your answer to 4 decimal places, e.g.1.7945.)
project 35
Using the following project information \ table [

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!