Question: Using the following table: ID Activity Early Start Late Start Duration (Days) R1, No of People Required R2, No of prople Required R1 and R2
Using the following table:
| ID | Activity | Early Start | Late Start | Duration (Days) | R1, No of People Required | R2, No of prople Required | R1 and R2 Rate=10/hr |
| A | Define Requirements | 0 | 0 | 4 | 2 | 2 |
|
| B | Design Application | 4 | 4 | 2 | 4 | 2 |
|
| C | Draft User Manual | 4 | 10 | 2 | 3 | 2 |
|
| D | Prepare Code | 6 | 6 | 4 | 6 | 2 |
|
| E | Test Code
| 10 | 10 | 2 | 4 | 2 |
|
| F | Correct Code
| 12 | 12 | 3 | 2 | 2 |
|
What is the cost of activity D?
| $2720 | ||
| $2560 | ||
| $4260 | ||
| $1820 |