Question: Using the following the data: Activity A B C D E F G H J K L M Immediate predecessor none none A &


Using the following the data: Activity A B C D E F G H J K L M Immediate predecessor none none A & B U E U D,G & F D & F H 1 & J K & J L Normal time in weeks 3 4 1 6 5 2 5 3 4 3 2 4 5 1)Draw the project network precedence diagram 2) show critical path.