Question: Using the forward and backward pass method, identify the Critical Path and total duration for the following network. Show all work. Task Duration Predecessor a
- Using the forward and backward pass method, identify the Critical Path and total duration for the following network. Show all work.
| Task | Duration | Predecessor |
| a | 5 |
|
| b | 10 | a |
| c | 10 | a |
| d | 5 | b |
| e | 3 | c |
| f | 10 | d, e |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock