Question: Using the grid technique, determine the least-cost location for the following problem: Tons Rate Grid Coordinates (H, V) S1 300 0.50 2, 14 S2 200
Using the grid technique, determine the least-cost location for the following problem:
| Tons | Rate | Grid Coordinates (H, V) | |
| S1 | 300 | 0.50 | 2, 14 |
| S2 | 200 | 0.60 | 6, 10 |
| M1 | 100 | 2 | 2, 2 |
| M2 | 100 | 1 | 10, 14 |
| M3 | 100 | 2 | 14, 18 |
| M4 | 100 | 1 | 14, 6 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts