Question: Using the gross requirements schedule below , prepare an alternative ordering system that orders every 3 weeks for 3 weeks ahead (a periodic order quantity).

Using the gross requirements schedule below , prepare an alternative ordering system that orders every 3 weeks for 3 weeks ahead (a periodic order quantity). What is the cost of this ordering system? Holding cost =$1/ unit / week; setup cost =$150; lead time =1 week; beginning inventory =25 units. Prepare a net requirements plan (enter your responses as whole numbers). The cost of this ordering system is $ (enter your response as a whole number)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
