Question: Using the gross requirements schedule below , prepare an alternative ordering system that always orders 100 units the week prior to a shortage (a fixed

Using the gross requirements schedule below , prepare an alternative ordering system that always orders 100 units the week prior to a shortage (a fixed order quantity of 100 ). What is the cost of this ordering system? Holding cost =$1/ unit / week; setup cost =$200; lead time =1 week; beginning inventory =25 units. Prepare a net requirements plan (enter your responses as whole numbers). The holding cost of this ordering system is $ (enter your response as a whole number). The setup cost of this ordering system is $ (enter your response as a whole number). The cost of this ordering system is $ (enter your response as a whole number)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
