Question: Using the information below and determine the following. JOB Processing Time(days) Due Date (days) A 4 11 B 6 5 C 3 1 D 2
Using the information below and determine the following.
JOB Processing Time(days) Due Date (days)
A 4 11
B 6 5
C 3 1
D 2 8
E 5 7
Using the dispatching rule SPT and calculate the average flow time.
Use the dispatching rule SPT and calculate average lateness.
Use the dispatching rule EDD and calculate the average flow time.
Use the dispatching rule EDD and calculate the average lateness.