Question: Using the information below, determine the following: Use the dispatching rule SPT and calculate the average flow time - Use the dispatching rule SPT and
Using the information below, determine the following:

Use the dispatching rule SPT and calculate the average flow time -
Use the dispatching rule SPT and calculate the average lateness -
Use the dispatching rule EDD and calculate the average flow time -
Use the dispatching rule EDD and calculate the average lateness -
Use the dispatching rule FCFS and calculate the average flow time -
Use the dispatching rule FCFS and calculate the average lateness -
Calculate the total make-span
Job A B D E Processing Time (hrs. 17 10 5 7 11 Hour (due) 15 25 20 32 38Step by Step Solution